Critical Action Planning – Rock Simple Capacity and Skills Planning

@tags:: #lit✍/📰️article/highlights
@links::
@ref:: Critical Action Planning – Rock Simple Capacity and Skills Planning
@author:: jaycaplan.com

2023-12-06 jaycaplan.com - Critical Action Planning – Rock Simple Capacity and Skills Planning

Book cover of "Critical Action Planning – Rock Simple Capacity and Skills Planning"

Reference

Notes

Quote

Now, list the Available Resources to work the Project Tasks in the plan. We want our Available Resources to be apples-to-apples with our Plan. If our plan calls for us to manage an outside vendor, we don’t estimate the vendor’s Work-units in our plan and we don’t include the vendor’s resources as Available Resources for our project. If, on the other hand, we have a full-time consultant working on the project, we do include the consultant’s Work-units in our plan and we do include the consultant’s resources as Available Resources for our project.
- No location available
-

Quote

For each Available Resource, we estimate the Available capacity, recognizing that individuals take time off, attend meetings and do training, and need to support non-project activities. As I’ve mentioned previously, I assume 3.5 to 4 work-days available per person per week.
- No location available
-

Quote

Another way to analyze your critical action plan is to add a skill-type for each task. Skill types could be function (e.g. mech eng, product manager, quality eng, etc) or activity (e.g. designing, testing, analyzing) or anything else you choose. You can then sum up scope by skill-type, and compare the result to your capacity by skill type. This technique identifies skill set deficits and might be useful for hiring or training.
- No location available
-